Leasing the hardware: GPUs and satellites
Can a satellite be financed the way a GPU fleet is?
- InfraCompute
- InfraOrbit
Where it holds Our reading
Both separate owning a costly, specialised asset from using it, and both rest on the user's credit and the contract that pays for the asset. Orbital computing is where the two meet: the SLI and Sophia Space framework, not yet signed, would have a lessor own computing satellites and lease them out.
Where it does not Our reading
A GPU can be taken back and sold. A satellite in orbit cannot be recovered, so a satellite lessor relies on control of the satellite, insurance and the lessee's credit rather than on repossession.
GPUs43 on file
Satellites and ground stations8 on file
- Banks
- Private credit
- Capital markets
- Lessors and equipment finance
- Lender not on file
| Point | GPUs | Satellites and ground stations |
|---|---|---|
| What the financier holds | Title to the GPUs under a lease, or security over them under a loan, usually with the customer contract assigned as well. | Title to the satellite or ground station, bought from the manufacturer or the operator, then leased to the user or used to serve it. |
The rest of this page sets out every point of each comparison and the records behind each chart, with their sources. It is free with a work email, along with the full tools and guides.
Read every comparison
Free. Work emails only. Unsubscribe at any time.
| Point | GPUs | Satellites and ground stations |
|---|---|---|
| Who lends, from the register | ||
| Life of the asset against the term | ||
| Taking the asset back | ||
| Registering the interest | ||
| Insurance | ||
| When payments start |
On the registers
GPU-backed loans and leases
Satellite and ground station leasing and sale-and-service deals
2
Building, then refinancing: project finance and asset-backed finance
Does the data centre route from construction loan to ABS exist in space or defence?
- InfraCompute
- InfraOrbit
Where it holds Our reading
In data centres both stages are on the register: construction and development debt while the campus is built, then ABS and CMBS once it is leased and earning. Satellites have the first stage: export credit backed financing for manufacture and launch.
Where it does not Our reading
There is no satellite ABS on the InfraOrbit register, so satellite operators refinance in the bond and bank markets as companies. In defence, the nearest structures on the register are long concessions for bases and housing, with no take-out market behind them.
Construction96 on file
ABS and CMBS133 on file
Satellite build and launch14 on file
- Banks
- Private credit
- Capital markets
- Export credit, development and government lenders
- Lessors and equipment finance
- Lender not on file
| Point | Construction | ABS and CMBS | Satellite build and launch |
|---|---|---|---|
| What the lender relies on | The campus's future cash flow, the construction contracts, sponsor support and the signed lease. | The cash flow of leased, operating data centres held by a special purpose issuer, rated by the agencies. | The cover of an export credit agency, which takes most of the risk, and the operator's own credit. |
| Point | Construction | ABS and CMBS | Satellite build and launch |
|---|---|---|---|
| Who lends, from the register | |||
| When it is used | |||
| Tenor and repayment | |||
| Where the comparison stops |
On the registers
Data centre construction and development debt
Data centre ABS and CMBS
Export credit backed satellite financings
3
Who pays: government and commercial offtake
How does lending against a government contract differ from lending against a hyperscaler contract?
- InfraDefence
- InfraOrbit
- InfraCompute
Where it holds Our reading
In both, the debt is sized to the contract behind it: the customer's credit, the length of the contract and how it can end. The registers hold both: housing, base and constellation financings paid for by governments, and data centre and GPU debt backed by a named hyperscaler or investment grade customer.
Where it does not Our reading
A government customer can usually end a contract for its own convenience and pays from budgets voted year by year, so lenders weigh the priority of the programme and the strength of the contractor, not the contract alone. A commercial contract ends only on the grounds it sets out.
Defence2 on file
Space2 on file
Data centres and GPUs6 on file
- Banks
- Capital markets
- Export credit, development and government lenders
| Point | Defence | Space | Data centres and GPUs |
|---|---|---|---|
| Who pays | A ministry of defence or an agency, under a concession or a public-private partnership. | A government or the European Union, under a concession or as the anchor customer of a programme. | A hyperscaler or another investment grade customer, under a lease or a capacity contract. |
| Point | Defence | Space | Data centres and GPUs |
|---|---|---|---|
| Who lends, from the register | |||
| How the contract can end | |||
| Budget risk | |||
| Assigning payments to lenders |
On the registers
Defence financings with a government as the customer
Space financings with a government as the customer
Debt backed by a named hyperscaler or investment grade customer
We are happy to talk through how a structure from one of these sectors can work in another. Contact us.
Each chart counts the records on a register that use the structure, one square for each, grouped by who lends as the register records it. InfraOrbit figures are live; figures from the other registers are as at the date shown under each list. A comparison is shown only where both sides are on a register, and each says where it stops.
* General information drawn from public sources only, not legal or investment advice. It is not our view of what is market. Each register counts only what has been made public, so a short list means little is public, not that little has been done.